Ready-for-Takeover

Terminology status: CurrentRFT

Also: Takeover

Quick definition: A contractual milestone introduced in CCDC 2 (2020) that marks when the owner can take over the work, reached once specified conditions — including certified substantial performance and occupancy permission — are met and verified by the consultant.

Explanation

Technical explanation

Under CCDC 2 (2020) GC 12.1, Ready-for-Takeover requires the consultant's certification of substantial performance and evidence of compliance with occupancy requirements; other listed items (such as final cleaning, operation and maintenance documents, as-built drawings, start-up testing, and demonstration and training) can be deferred by agreement or for reasons beyond the contractor's control. The contractor applies in writing listing remaining items; the consultant has 10 days to confirm the date or give reasons. Contract Time now runs to the Ready-for-Takeover date, and indemnity and waiver-of-claims timing reference it.

Practical example

A community centre reaches substantial performance on 2 May, but the occupancy permit is issued on 16 May. Ready-for-Takeover is confirmed for 16 May, with training sessions deferred by agreement to the following week.

Why it matters

Ready-for-Takeover links the contract's completion date to the owner's real ability to use the facility, including handover information — a natural hook for asset-information requirements.

Common confusion

Ready-for-Takeover is a contractual milestone in CCDC 2; Substantial performance is a statutory one under lien legislation. Ready-for-Takeover cannot occur before substantial performance is certified.

Standards and references

  1. CCDC 2 (2020): 8 Key Changes to the Stipulated Price Contract. McInnes Cooper, 2021.Widely accepted professional interpretation
    Supports: GC 12.1 conditions; mandatory and deferrable items; 10-day consultant response; indemnity and waiver timing
  2. CCDC 2 2020 — CCDC 2 – 2020 Stipulated Price Contract. Canadian Construction Documents Committee (CCDC), 2020. Definitions (Ready-for-Takeover, Contract Time).Original VDC Stack.io wording, based on the standard
    Supports: Ready-for-Takeover reached when GC 12.1 conditions met and verified; Contract Time runs to Ready-for-Takeover · Status: Definitions and GC numbering reviewed from a copy included in a public tender package; confirm against a licensed copy.

VDC Stack.io writes its own explanations and does not reproduce copyrighted standards text. Consult the cited standard for normative wording.

Cite this entry

Show citation text

VDC Stack.io. (2026). Ready-for-Takeover. In VDC Stack.io Knowledge Dictionary. Retrieved from https://vdcstack.io/dictionary/ready-for-takeover/