Schedule baseline
Also: Baseline schedule, Baseline
Quick definition: The approved version of the project schedule, frozen as the reference against which actual progress and changes are measured.
Explanation
Beginner explanation
Once everyone agrees the plan, a copy is saved as the baseline. Later, the live schedule is compared with it to see what has slipped, by how much, and why.
Technical explanation
A baseline is normally accepted by the owner or consultant early in the contract and changed only through formal change control. Progress updates record actual dates and remaining durations in the current schedule; variance against the baseline exposes slippage. Contracts usually require a baseline submission, periodic updates and a narrative explaining critical-path changes. Re-baselining is a formal decision, not a routine update. The schedule baseline is one of the reference points (with scope and cost) used in Earned value management.
Practical example
A school board accepts the contractor's baseline in month two. By month nine the update shows the roofing milestone 18 days behind the baseline, and the narrative attributes 10 days to a change directive for added skylights. That analysis supports an extension request.
Why it matters
Without a baseline there is nothing objective to measure delay against, which makes time claims hard to evaluate.
Standards and references
- A Guide to the Project Management Body of Knowledge (PMBOK Guide), Eighth Edition. Project Management Institute (PMI), 2025.Widely accepted professional interpretation
Supports: Schedule performance domain; baselines as the reference for measuring performance in PMI practice · Status: Published November 2025; six principles and seven performance domains (governance, scope, schedule, finance, stakeholders, resources, risk).
VDC Stack.io writes its own explanations and does not reproduce copyrighted standards text. Consult the cited standard for normative wording.
Cite this entry
Show citation text
VDC Stack.io. (2026). Schedule baseline. In VDC Stack.io Knowledge Dictionary. Retrieved from https://vdcstack.io/dictionary/schedule-baseline/