Look-ahead schedule

Terminology status: Established

Also: Three-week look-ahead, Lookahead plan, Short-interval schedule

Quick definition: A short-interval schedule, typically covering the next three to six weeks, that breaks upcoming work into detailed tasks so constraints can be identified and removed before the work starts.

Explanation

Technical explanation

The look-ahead is derived from the CPM master schedule and updated weekly with the trades. Its purpose is make-ready planning: each upcoming task is screened for constraints (design information, approvals, materials, equipment, preceding work, space, labour) and actions are assigned to clear them. In the Last Planner System the look-ahead sits between phase pull plans and weekly work plans.

Practical example

The three-week look-ahead for level 6 shows drywall starting in week 3, but the screening shows the fire-stopping inspection is not booked and the board delivery date is unconfirmed. Both actions are assigned at the coordination meeting.

Why it matters

Most site delays come from constraints that were visible weeks earlier. A look-ahead turns the schedule into actionable preparation.

Standards and references

  1. Last Planner System — Introduction and Principles. Lean Construction Institute.Widely accepted professional interpretation
    Supports: Lookahead planning, constraint identification and removal within the Last Planner System

VDC Stack.io writes its own explanations and does not reproduce copyrighted standards text. Consult the cited standard for normative wording.

Cite this entry

Show citation text

VDC Stack.io. (2026). Look-ahead schedule. In VDC Stack.io Knowledge Dictionary. Retrieved from https://vdcstack.io/dictionary/look-ahead-schedule/