Change order vs change directive vs supplemental instruction

Three CCDC 2 instruments for changing or clarifying the work. Which one applies depends on whether price or time change, and whether they are agreed yet.

AspectSupplemental instructionChange directiveChange order
Issued byConsultantConsultant, signed by the ownerSigned by owner and contractor
Changes price or time?NoYes, but not yet agreedYes, agreed
When usedClarification consistent with contract intentWork must proceed before price or time is settledPrice and time adjustment agreed
What happens nextContractor proceeds (or notifies if it disagrees there is no impact)Valued later, then recorded in a change orderBecomes part of the contract
AIA equivalentMinor change / architect's supplemental instructionConstruction change directiveChange order

The practical takeaway

If an RFI answer costs money or time, it is not a supplemental instruction. Ask for a change directive or a change order before you proceed.

Full definitions

  • Change order — A written amendment to the construction contract, signed by the owner and contractor, recording an agreed change in the work together with any adjustment to the contract price and time.
  • Change directive — A written instruction from the consultant, signed by the owner, directing the contractor to proceed with a change to the work before the price and time adjustments have been agreed.
  • Supplemental instruction — An instruction from the consultant — usually drawings, specifications or a written note — that clarifies or adds detail to the work without changing the contract price or contract time.
  • Request for information (RFI) — A formal written question from the contractor to the design consultant asking for clarification of the contract documents — typically about design intent, an apparent omission or a conflict.